Project Sugar

With our highly efficient approach, BZI stands out as the industry leader in steel erection for warehouse and distribution projects.

  • 5/22 - 9/22
    DURATION
  • CEDAR CITY, UT
    LOCATION
  • 3.8MM
    SQUARE FEET

Challenge

BZI faced a tighter schedule than ever before with Project Sugar. Not only did the team face a tight deadline, but weather factors such as lightning, wind, freezing temperatures and snow threatened to delay progress.  Additionally, the team couldn’t use their normal approach to sequencing, which meant finding additional ways to innovate on the job site to create efficiency. Despite this, the team consistently installed an impressive 60-70 panels per day.  

Outcome

Project Sugar achieved a milestone as the fastest ARS prototype erected by BZI, boasting an impressive 74,000 working hours without a single lost-time incident. 

Scopes

  • Structural steel - 25,000 tons
  • Main core structure delivered in 16 weeks
  • IMP installation - 230,000 square feet
  • Strategic problem solving

LET’S WORK TOGETHER

BZI accelerates project delivery and improves safety. Ready to learn how we can bring our proven approach to innovation, teamwork, and action to your next project?

Get in Touch

“This would be a quote about the innovation featured above or about innovation at BZI overall. The speaker would be a GC or customer."

First Lastname
Customer Company Project Superintendent