An innovative and out-of-the-way bracing solution designed to keep pace with the size and scale of today’s buildings.
Completion
2022
Square Footage
3.8 million
Location
Loveland, CO
Tonnage
25,000
Duration
20 weeks (May-Sep)
Woodburn, Oregon
22,000
28 weeks (Sep - Mar)
2021
2.9 million
Davenport, Iowa
42,000
12 weeks (Oct-Jan)